MEPCO New Connection

Last checked 26 September 2026

MEPCO New Connection title card: Apply, documents and timeline

You can apply for a new MEPCO electricity connection from your phone or at a MEPCO office. Here is the route that works today, what to attach, and what happens between your application and your first bill.

Where to apply in 2026. MEPCO's website still points its "Apply Online" button to the ENC portal (enc.com.pk). The ENC portal itself now tells all MEPCO users to use the MEPCO Smart App, the PowerSmart app and e-OPS, or to visit the nearest customer facilitation centre. Checked 26 September 2026.

NEPRA's Consumer Service Manual gives MEPCO 30 days from registration to connect a load of up to 15 kW, and the demand notice is due within the first 10 days. The MEPCO consumer services guide lists the timeframes for larger loads.

Timeline of a MEPCO new connection up to 15 kW: 4, 6, 11 and 9 days, 30 days in total
NEPRA timeframe for connections up to 15 kW at 400 V (Consumer Service Manual, Annexure III).

Ways to apply

1. MEPCO SMART app

MEPCO's app lists a new connection service ("apply new connection with ease from anywhere") and a Track New Connection service. Get it on the App Store or Google Play.

2. Customer facilitation centre

Take the filled form and documents to the nearest MEPCO customer facilitation centre or your sub-division office. Circle phone directories are on MEPCO's contact page.

3. The paper form

MEPCO publishes its new connection application form (PDF, Urdu). It covers domestic and commercial single-phase connections up to 4 kW.

What the application form asks for

Documents to attach

  1. Proof that you own the premises.
  2. An attested copy of your CNIC.
  3. If you are a tenant: the owner's permission letter with attested proof of the owner's ownership.

What you agree to when you sign

What happens after you apply

  1. Registration. MEPCO registers the application and gives you a registration number.
  2. Document check. The office checks your documents and returns the application if anything is missing.
  3. Site check. The connection section checks whether the existing transformer can take the load or new equipment is needed.
  4. Dues check. MEPCO confirms that no old dues are outstanding at the premises.
  5. Demand notice. Once everything is verified, MEPCO issues a demand notice with the amount to pay for the connection. See the demand notice guide and the security deposit rates per kW.
  6. Connection. After you pay, the meter is installed and your first bill follows.

Choosing the right load

Ask for a load that matches your appliances. Your monthly fixed charge is worked out on the sanctioned load, from Rs 200 to Rs 675 per kW. If you need more load later, see MEPCO load extension. At 5 kW and above, a home gets a time-of-use meter with peak-hour rates. The tariff page has the full rate table.

Pay only through official channels. PITC warns never to send money for a new connection to anyone's personal Easypaisa, JazzCash or bank account. Report such requests to the 118 helpline.

Sources: MEPCO new connection page and application form (mepco.com.pk), MEPCO mobile app page, ENC portal notice (enc.com.pk), MEPCO FAQ page, NEPRA determination of MEPCO's supply tariff (7 January 2026), PITC complaint portal warning.

Frequently asked questions

Can I apply for a MEPCO connection online?
Yes. The MEPCO SMART app has a new connection service and a tracker for your application. The ENC portal now directs MEPCO applicants to the MEPCO SMART app, the PowerSmart app or a customer facilitation centre.
What documents do I need for a new MEPCO connection?
MEPCO's application form asks for proof that you own the premises and an attested copy of your CNIC. A tenant also needs the owner's permission letter with attested proof of the owner's ownership.
How do I track my new connection application?
Use Track New Connection in the MEPCO SMART app, or ask the office where you applied.
Which meter will my home get?
Homes are billed on the residential tariff A-1. If the sanctioned load is 5 kW or more, MEPCO fits a time-of-use meter with peak and off-peak rates.
How do I change the name on my MEPCO connection?
MEPCO's FAQ says a change of name follows the same instructions as a new connection. The MEPCO SMART app also lists a request to change the owner name, load or tariff of an existing connection.